Page 558 - National Electrical Price Guide
P. 558
08-27-19
280-56
DEMOLITION - Motor Control Removal
LABOR HOURS
Description LOW MED HIGH X-HIGH
Remove Size 0 - Size 2 Starter 0.80 1.00 1.20 1.40
Remove Size 3 - Size 4 Starter 1.20 1.50 1.80 2.10
Remove Size 5 Starter 3.60 4.50 5.40 6.30
Remove Size 6 Starter 6.40 8.00 9.60 11.20
Remove Size 7 Starter 7.00 8.75 10.50 12.25
Remove Push Button Station 0.60 0.75 0.90 1.05
Remove Time Clock 0.60 0.75 0.90 1.05
DEMOLITION - Contactor Removal
LABOR HOURS
Description LOW MED HIGH X-HIGH
Remove 30A - 100A Contactor 0.80 1.00 1.20 1.40
Remove 200A - 300A Contactor 2.40 3.00 3.60 4.20
Remove 400A Contactor 3.40 4.25 5.10 6.00
Remove 600A Contactor 5.00 6.25 7.50 8.75
Remove 800A Contactor 6.00 7.50 9.00 10.50
DEMOLITION - Transformer Removal
LABOR HOURS
Description LOW MED HIGH X-HIGH
Remove 9 KVA Transformer 3.00 3.75 4.50 5.25
Remove 15 KVA Transformer 4.00 5.00 6.00 7.00
Remove 30 KVA Transformer 5.00 6.25 7.50 8.75
Remove 45 KVA Transformer 8.00 10.00 12.00 14.00
Remove 75 KVA Transformer 9.00 11.00 13.00 15.00
Remove 112.5 KVA Transformer 10.00 12.00 15.00 17.00
Remove 150 KVA Transformer 12.00 15.00 18.00 21.00
Remove 225 KVA Transformer 13.00 16.00 19.00 23.00
Remove 300 KVA Transformer 14.00 17.00 21.00 24.00
Remove 500 KVA Transformer 20.00 25.00 30.00 35.00
Remove 750 KVA Transformer 30.00 37.00 45.00 52.00
Remove 1000 KVA Transformer 38.00 47.00 57.00 66.00
DEMOLITION - Panelboard Removal
LABOR HOURS
Description LOW MED HIGH X-HIGH
Remove 100A Panel 4.00 5.00 6.00 7.00
Remove 125A Panel 4.00 5.00 6.00 7.00
Remove 150A Panel 6.00 7.50 9.00 10.50
Remove 200A Panel 6.00 7.50 9.00 10.50
Remove 225A Panel 6.00 7.50 9.00 10.50
Remove 400A Panel 7.00 9.00 10.00 12.00
Remove 600A Panel 10.00 12.00 15.00 17.00
Remove 800A Panel 11.00 13.00 16.00 19.00
Remove 1200A Panel 12.00 15.00 18.00 21.00
NPG/NSG LABOR UNITS ARE PER EACH
25A-2 COPYRIGHT © 1996-2019 by ELECTRICAL RESOURCES, INC.