DEMOLITION - Switchboard Removal
LABOR HOURS
Description LOW MED HIGH X-HIGH
Remove 800A Switchboard 11.00 13.00 16.00 19.00
Remove 1200A Switchboard 12.00 15.00 18.00 21.00
Remove 1000A Switchboard 16.00 20.00 24.00 28.00
Remove 1200A Switchboard 16.00 20.00 24.00 28.00
Remove 1600A Switchboard 18.00 22.00 27.00 31.00
Remove 2000A Switchboard 20.00 25.00 30.00 35.00
Remove 2500A Switchboard 22.00 27.00 33.00 38.00
Remove 3000A Switchboard 24.00 30.00 36.00 42.00
Remove 4000A Switchboard 30.00 37.00 45.00 52.00
DEMOLITION - GRC Conduit Removal
LABOR HOURS
Description LOW MED HIGH X-HIGH
Remove 1/2" - 1" GRC 0.03 0.04 0.05 0.06
Remove 1-1/4" - 2" GRC 0.06 0.08 0.09 0.11
Remove 2-1/2" - 3" GRC 0.10 0.13 0.15 0.20
Remove 3-1/2" - 4" GRC 0.12 0.15 0.18 0.21
Remove 5" - 6" GRC 0.15 0.20 0.23 0.25
DEMOLITION - IMC Conduit Removal
LABOR HOURS
Description LOW MED HIGH X-HIGH
Remove 1/2" - 1" IMC 0.03 0.04 0.05 0.06
Remove 1-1/4" - 2" IMC 0.05 0.06 0.08 0.09
Remove 2-1/2" - 3" IMC 0.08 0.10 0.12 0.14
Remove 3-1/2" - 4" IMC 0.10 0.13 0.15 0.20
DEMOLITION - EMT Conduit Removal
LABOR HOURS
Description LOW MED HIGH X-HIGH
Remove 1/2" - 1" EMT 0.02 0.03 0.04 0.05
Remove 1-1/4" - 2" EMT 0.04 0.05 0.06 0.07
Remove 2-1/2" - 3" EMT 0.07 0.09 0.11 0.12
Remove 3-1/2" - 4" EMT 0.10 0.13 0.15 0.20
DEMOLITION - Wire Removal
LABOR HOURS
Description LOW MED HIGH X-HIGH
Remove #18 - #4 Wire 0.01 0.02 0.03 0.04
Remove #3 - #1 Wire 0.02 0.03 0.04 0.05
Remove #1/0 - #2/0 Wire 0.02 0.03 0.04 0.05
Remove #3/0 - #4/0 Wire 0.03 0.04 0.05 0.06
Remove #250 - #500 Wire 0.04 0.05 0.06 0.07
Remove #600 - #1000 Wire 0.04 0.05 0.06 0.07
NPG/NSG LABOR UNITS ARE PER EACH AND PER FOOT