Page 559 - National Electrical Price Guide
P. 559

08-27-19
                                                                                                               280-57
                                                           DEMOLITION - Switchboard Removal

                                                                                             LABOR   HOURS
                                                                 Description                  LOW    MED     HIGH   X-HIGH
                                    Remove 800A Switchboard                           11.00   13.00    16.00   19.00
                                    Remove 1200A Switchboard                         12.00    15.00    18.00   21.00
                                    Remove 1000A Switchboard                         16.00    20.00    24.00   28.00
                                    Remove 1200A Switchboard                         16.00    20.00    24.00   28.00
                                    Remove 1600A Switchboard                         18.00    22.00    27.00   31.00
                                    Remove 2000A Switchboard                         20.00    25.00    30.00   35.00
                                    Remove 2500A Switchboard                         22.00    27.00    33.00   38.00
                                    Remove 3000A Switchboard                         24.00    30.00    36.00   42.00
                                    Remove 4000A Switchboard                         30.00    37.00    45.00   52.00


                                                           DEMOLITION - GRC Conduit Removal
                                                                                             LABOR   HOURS
                                                                 Description                  LOW    MED    HIGH   X-HIGH
                                    Remove 1/2" - 1" GRC                               0.03   0.04     0.05     0.06
                                    Remove 1-1/4" - 2" GRC                            0.06    0.08     0.09     0.11
                                    Remove 2-1/2" - 3" GRC                            0.10    0.13     0.15     0.20
                                    Remove 3-1/2" - 4" GRC                            0.12    0.15     0.18     0.21
                                    Remove 5" - 6" GRC                                0.15    0.20     0.23     0.25

                                                           DEMOLITION - IMC Conduit Removal

                                                                                             LABOR   HOURS
                                                                 Description                  LOW    MED     HIGH   X-HIGH
                                    Remove 1/2" - 1" IMC                              0.03    0.04     0.05     0.06
                                    Remove 1-1/4" - 2" IMC                           0.05     0.06     0.08     0.09
                                    Remove 2-1/2" - 3" IMC                           0.08     0.10     0.12     0.14
                                    Remove 3-1/2" - 4" IMC                           0.10     0.13     0.15     0.20

                                                           DEMOLITION - EMT Conduit Removal
                                                                                             LABOR   HOURS
                                                                 Description                  LOW    MED     HIGH   X-HIGH
                                    Remove 1/2" - 1" EMT                             0.02     0.03      0.04    0.05
                                    Remove 1-1/4" - 2" EMT                           0.04     0.05      0.06    0.07
                                    Remove 2-1/2" - 3" EMT                           0.07     0.09      0.11    0.12
                                    Remove 3-1/2" - 4" EMT                           0.10     0.13      0.15    0.20

                                                               DEMOLITION - Wire Removal

                                                                                             LABOR   HOURS
                                                                 Description                  LOW    MED     HIGH   X-HIGH
                                    Remove #18 - #4 Wire                             0.01     0.02     0.03     0.04
                                    Remove #3 - #1 Wire                              0.02     0.03     0.04     0.05
                                    Remove #1/0 - #2/0 Wire                          0.02     0.03     0.04     0.05
                                    Remove #3/0 - #4/0 Wire                          0.03     0.04     0.05     0.06
                                    Remove #250 - #500 Wire                          0.04     0.05     0.06     0.07
                                    Remove #600 - #1000 Wire                         0.04     0.05     0.06     0.07












              NPG/NSG                                      LABOR UNITS ARE PER EACH AND PER FOOT
              25A-3                             COPYRIGHT © 1996-2019 by ELECTRICAL RESOURCES, INC.
   554   555   556   557   558   559   560   561   562   563   564