Page 22 - December Newsletter
P. 22

BIOCORK2                                                                                                                The extent of interfaces has been to the forefront
                                                                                                                              of  our  planning  since  the  outset  of  the
                                                                                                                              preconstruction  stage.  When  all  the  scope  is
                                                                                                                              considered, with the exception of a small portion
                                                                                                                              of  the  front  elevation  the  construction  works
                                                                                                                              interfaces  /  ties  into  the  rest  of  the  live
                                                                                                                              operational facility. The extent / significance of
                                                                                                                              this
                                                                                                                              this  cannot  be  fully  appreciated  even  from
                                                                                                                              aerial  drone  photography.  We  have  even
                                                                                                                              rerouted the on-site exercise route out site twice,
                                                                                                                              carried  out  two  road  crossings  on  the  main
                                                                                                                              incomes plant road operational 24 hours per day
                                                                                                                              and  had  to  relocate  the  General  Manager  of
                                                                                                                              the plant from his office to facilitate the canteen
                                                                                                                              expansion  construction.  Detailed  planning,
                                                                                                                              expansion
                                                                                                                              communication,  contractor  engagement  and
                                                                                                                              hands on management are crucial for successful
                                                                                                                              and  safe  execution  of  these  works,  whilst
                                                                                                                              ensuring no impact on the operational facilities.