1.5.  PLANNING


                   Planning of the replacement bridge started in 1997 with a cross-lake study conducted by

                   the state Department of Transportation. The study followed several others in the late 20th
                   century to find solutions to traffic on the SR 520 floating bridge, with  most proposals

                   rejected after heavy opposition from communities on both ends of the bridge.

                   The final environmental impact statement for the project was issued in 2011, allowing for
                   construction of the pontoons to begin the following year.




                    1.6.  FUNDING


                   Funding  was  allocated  to  major  phases  of  the  project  at  different  times.  The  western
                   portions of the project, in the City of Seattle, were the last to be funded. The $4.5 billion in

                   funding comes largely from the state gas tax earmarked for highways, tolling, and Federal
                   highway funds.


                   In 2014, the budget for the project was increased by $250 million to cover cost overruns.