Page 148 - Project+
P. 148

Analogous Estimating Analogous estimating also known as top-down estimating is

     a technique that uses actual durations from similar tasks on a previous project. This is
     most frequently used at the early stages of project planning, when you have limited
     information about the project. Although analogous estimating can provide a good
     approximation of task duration, it is typically the least accurate means of obtaining an
     estimate. No two projects are the same, and there is the risk that the project used to

     obtain the analogous estimates is not as similar to the current project as it appears.
     Results from analogous estimating are more accurate if the person doing the

     estimating is familiar with both projects and is able to understand the differences that
     could impact the activity durations on the new project.

     Expert Judgment Expert judgment is a technique where the people most familiar
     with the work determine the estimate. Ideally, the project team member who will
     perform the task should provide the estimate. If all the team members haven’t been
     identified yet, recruit people with expertise for the tasks you need estimated. Ask for

     people who have completed a similar task on a previous project to assist with the
     estimates for this project.

     Remember that people with more experience will likely provide a shorter estimate for
     an activity than someone who doesn’t have as much experience. You should validate
     the estimate or ask other experts in the department to validate it for you.

     Parametric Estimating Parametric estimating is a quantitatively based estimating
     method that multiplies the quantity of work by the rate. To apply quantitatively based

     durations, you must know the productivity rate of the resource performing the task or
     have a company or industry standard that can be applied to the task in question. The
     duration is obtained by multiplying the unit of work produced by the productivity rate.
     For example, if a typical cable crew can bury 5 miles of cable in a day, it should take 10
     days to bury 50 miles of cable.

     PERT The Program Evaluation and Review Technique (PERT) is a method that the
     U.S. Navy developed in the 1950s. The Navy was working on one of the most complex

     engineering projects in history at the time—the Polaris Missile Program—and needed a
     way to manage the project and forecast the project schedule with a high degree of
     reliability. PERT was developed to do just that.

     PERT and three-point estimates are similar techniques. The difference is that three-
     point estimates use an average estimate to determine project duration, while PERT
     uses what’s called expected value (or the weighted average). Expected value is

     calculated using the three-point estimates for activity duration and then finding the
     weighted average of those estimates.

     The formula to calculate expected value is as follows:

     (optimistic + pessimistic + (4 × most likely)) / 6

     Using the same numbers used in the three-point estimates produces the following




                                                            148
   143   144   145   146   147   148   149   150   151   152   153