FIGURE 6.1 Project organization chart

     You may also present the work of the project in an organization breakdown structure

     (OBS). This form of organization chart shows the departments, work units, or teams
     within an organization (rather than individuals) and their respective work packages.

     A resource breakdown structure (RBS) is another type of hierarchical chart that
     breaks down the work of the project according to the types of resources needed. For
     example, you might have painters, carpenters, and electricians as resource types on the
     RBS.


     Matrix-Based Charts


     A responsibility assignment matrix (RAM) is a matrix-based chart that maps your
     WBS elements to the required resources. Table 6.1 shows a sample portion of a RAM
     for an IT development project. It lists the WBS identifier, the type of resource required,
     and the number of resources needed for each skill set.


     TABLE 6.1 Sample project responsibility assignment matrix

           WBS identifier Programmer Tester Marketing Tech writer Server

           10–1–1–1                                                                 1

           10–1–1–2                2

           10–1–1–3                                     3                                              1
           10–1–1–4                4

           10–1–1–5                                                1


     Another type of responsibility assignment chart I like to use is called a RACI chart.
     These are used to show the types of resources and the responsibility they each have on




                                                            172