Traditional costing




               3.3  The over-/under-absorption

               This is calculated as:

               (Budgeted overhead rate per unit × actual units) – actual overheads incurred
               If this value is positive then overheads have been OVER absorbed, and if it is
               negative then overheads have been UNDER absorbed.








                  Example 2




                   Calculate the over-/under-absorption for Limco.

                   Solution

                   Overheads absorbed = $10 per unit × 21,000 units = $210,000

                   Actual overheads were $200,000

                   Over-absorbed = $210,000 – $200,000 = $10,000