Traditional costing
3.3 The over-/under-absorption
This is calculated as:
(Budgeted overhead rate per unit × actual units) – actual overheads incurred
If this value is positive then overheads have been OVER absorbed, and if it is
negative then overheads have been UNDER absorbed.
Example 2
Calculate the over-/under-absorption for Limco.
Solution
Overheads absorbed = $10 per unit × 21,000 units = $210,000
Actual overheads were $200,000
Over-absorbed = $210,000 – $200,000 = $10,000