                           Breach of contract





               Actual breach of contract

               Actual breach occurs at the time performance of the contract was due and happens
               when:


                    One party fails to put forward any sort of performance

                    The performance put forward is so inadequate the injured party is substantially
                     deprived of the whole benefit of the contract.


               Anticipatory breach


                             This takes place where, before the due date for performance of the
                             contract, one party states or shows by his actions that he will not be
                             performing the contract.

                             Anticipatory breach occurs when:


                                  One of the parties declares before the date of performance that he
                                   has no intention of carrying out his duties. This is known as
                                   express anticipatory breach.

                                  One of the parties does something which makes the performance
                                   of the contract impossible. This is known as implied anticipatory
                                   breach.