Chapter 24









                   Example 2 cont.




                   Workings

                   (W1) Contract profit

                                                                       $m         $m
                   Contract price                                                    30

                   Costs to date                                         14
                   Costs to complete                                       7

                                                                     ———
                                                                                    (21)

                                                                                ———
                   Contract profit                                                    9

                                                                                ———



                   (W2) Stage of completion
                   Cost basis: cost to date/total cost                14/21     66.7%



                   (W3) Contract asset                                            $m

                   Cost to date                                                      14
                   Profit to date                                                     6
                   Received from customer                                           (12)

                                                                                ———

                                                                                      8
                                                                                ———