               7.2 Budget centres

               Each budget centre is often a responsibility centre. Each centre will have its own
               budget and a manager will be responsible for managing the centre and controlling
               the budget. This manager is often referred to as the budget holder. Regular
               budgetary control reports will be sent to each budget holder so that they may monitor
               their centre’s activities and take control action if necessary.

               The budgetary reporting system should ideally be based on the exception principle
               which means that management attention is focused on those areas where
               performance is significantly different from budget.


               There are four classifications for responsibility centres, depending on what the
               manager of the centre has responsibility for:

                    Cost centre – manager is responsible for operating costs.


                    Revenue centre – manager is responsible for revenue.

                    Profit centre – manager is responsible for operating costs and revenue and the
                     resulting profit.

                    Investment centre – manager is responsible for profit and the return on any
                     investment made.