Budgeting




               The flexed budget (budget cost allowance) is calculated as follows:

                 Fixed costs: no change

                 Variable costs:
                                                       Budgeted cost
                Budgeted cost allowance =           —————————                  × Actual activity level
                                                   Budgeted activity level
                 Semi-variable costs: The fixed element will not change and the variable element
                 will be flexed as above.