Capital budgeting
To calculate the IRR:
Calculate two NPVs for the project at two different costs of capital. The higher
the discount rate – the lower the NPV will be.
Use the following formula to find the IRR:
N L
IRR = L + ——— (H – L)
N L – N H
where: L = lower discount rate
H = higher discount rate
NL = NPV at the lower discount rate
NH = NPV at the higher discount rate.