Capital budgeting




                           X plc has the following estimated net cash flows for a new project.

                           X’s cost of capital is 10% per annum (round answers to the nearest £000).

                                             Year 0       Year 1       Year 2       Year 3

                                              £000         £000         £000         £000

               Capital expenditure                500
               Disposal proceeds                                                         50
               Revenue                                        400           500         300

               Operating costs                                100           150         110

               Discount factors                 1.000        0.909         0.826      0.751
               Calculate the net present value for the project.


                                            Year 0       Year 1       Year 2        Year 3

                                             £000         £000         £000          £000
               Capital
               expenditure/disposal        –500                                      50
               Revenue                                  400            500          300
               Operating costs                         –100          –150         –110

               Net cash flows              –500         300            350          240

               PV factors                      1.000       0.909         0.826        0.751
               Discounted cash flows       –500         273            289          180

               Net present value            242




                  Illustrations and further practice


                  Now try TYU question 9 from Chapter 14