F2: Advanced Financial Reporting




               The following data relates to the next 2 questions.


               A contract to build a new football stadium has commenced during the year ended
               30th June 20X9. The following figures relate  to the contracts current estimates of
               progress:

                                                                        $
               Contract price                                        800,000
               Cost incurred to date                                 470,000

               Expected costs to complete                            560,000
               Work certified as completed                               45%
               Progress billings to date                             400,000

               The company uses the output (work certified as complete) basis for determining
               progress towards completion.



               7.3  What amounts will be shown for revenue and cost of sales within the
                     statement of P/L for the year ended 30th June 20X9?

                     A     Revenue $360,000, Cost of sales $463,500

                     B     Revenue $360,000, Cost of sales $590,000

                     C     Revenue $800,000, Cost of sales $470,000


                     D     Revenue $800,000, Cost of sales $1,030,000


               7.4  What amounts will be shown on the statement of financial position for the
                     contract asset/liability as at the year ended 30th June 20X9?

                     A     Contract asset $300,000

                     B     Contract asset $400,000

                     C     Contract liability $33,550

                     D     Contract liability $160,000