Page 426 - PM Integrated Workbook 2018-19
P. 426
Chapter 15
Example 3
The first unit of a new product is expected to take 100 hours. An 80% learning
curve is known to apply.
Calculate:
(a) The average time per unit for the first 16 units
a = 100 b = –.03219 x = 16
Y = 100 × 16 –.03219
Y = 40.96 hours
(b) The average time per unit for the first 25 units
x = 25
Y = 100 × 25 –.03219
Y = 35.48 hours
(c) The time it takes to make the 20th unit
x = 20 Y = 100 × 20 –.03219 Y = 38.12399855 hours
Total time for 20 units = 38.12399855 × 20 = 762.48 hours
x = 19 Y = 100 × 19 –.03219 Y = 38.75870124 hours
Total time for 19 units = 38.75870124 × 19. = 736.42 hours
So, to make the 20th unit, 762.48 – 736.42 = 26.06 hours