Chapter 15









                   Example 3





                   The first unit of a new product is expected to take 100 hours. An 80% learning
                   curve is known to apply.

                   Calculate:

                   (a)  The average time per unit for the first 16 units

                        a = 100                     b = –.03219                  x = 16


                                                    Y = 100 × 16  –.03219


                                                    Y = 40.96 hours
                   (b)  The average time per unit for the first 25 units

                        x = 25


                        Y = 100 × 25   –.03219

                        Y = 35.48 hours

                   (c)  The time it takes to make the 20th unit


                        x = 20               Y = 100 × 20  –.03219        Y = 38.12399855 hours
                        Total time for 20 units = 38.12399855 × 20 = 762.48 hours


                        x = 19               Y = 100 × 19  –.03219        Y = 38.75870124 hours

                        Total time for 19 units = 38.75870124 × 19. = 736.42 hours

                        So, to make the 20th unit, 762.48 – 736.42 = 26.06 hours


















               418