                   Irwin manufactures two different types of computer with the following details:

                                                                           Computer  Computer
                                                                                X           Y
                   Selling price per unit                                      $800      $1,200
                   Component costs per unit                                    $150        $310
                   Assembly time (in minutes per unit)                           80          130
                   Testing time (in minutes per unit)                           120          180
                   Packaging time (in minutes per unit)                          60           30
                   Maximum demand (units)                                       300          800
                   It expects assembly time to be limited to 1,000 hours and testing time to be
                   limited to 875 hours.

                   The following costs are derived from Irwin’s budgets to 31st December:

                   Assembly           $180/hour


                   Testing            $60/hour

                   Packaging          $20/hour

                   Define the variables for a linear programming solution for Irwin’s
                   production constraints.

                   Solution

                   Let x = each unit of Computer X produced

                   Let y = each unit of Computer Y produced

                   Let C = the contribution to be maximised