Supplementary objective test questions




               2.7  ABC has the following information about its 3 products:
                     Product                          A           B           C
                                                      $           $           $
                       Sales price                    100          75           80
                     Material cost                     32          20           15
                     Labour ($10 per hour)             30          20           15
                     Variable overhead                  5          15           18
                     Fixed overhead                     5          10           20
                                                   –––––       –––––        –––––
                     Profit per unit                   28          10           12
                     Demand                         1,000       2,000       3,000
                     Current production plan          500            0      3,000
                     Labour is a scarce resource and the current production plan has correctly
                     utilised the available labour to maximise contribution.


                     If ABC were able to source more labour, what would be the shadow price
                     per hour of labour for Product A?

                     A     $0


                     B     $10

                     C     $11

                     D     $21


               2.8  A firm of surveys provides teams of staff on two types of service, industrial
                     premise surveys (P) and commercial premise surveys (C).  Both services use a
                     combination of junior and senior surveyors, which are both in short supply, and
                     each service needs a total of 10 staff hours.

                     Industrial premise surveys require one junior surveyor hour for each senior
                     surveyor hour, whereas commercial premise surveys require 4 junior surveyor
                     hours for each senior surveyor hour.

                     Assuming that only 50,000 hours of junior surveyor time will be available,
                     what is the constraint on service provision imposed by junior surveyors?

                     A     5P + 8C ≤ 50,000

                     B     P + 4C ≤ 50,000

                     C     5P + 2C ≤ 50,000


                     D     P + 5C ≤ 50,000