Page 4 - ENGINEERING
P. 4

2. Performance of track renewal works:




                                                                                          Progress
                                                                                                        % of
                                                                                Target
       S.                                                Target     Progress              21-22         Progress
       No    Item                            Unit        2020-21    2020-21     2021-                   over target
                                                                                22
                                                                                          (Upto         2021-22
                                                                                          22.10.21)

                                             CTR
       1     Track Renewal                               7.88       5.425       12.43     2.515         20.23 %
                                             Units


             a)Through Rail Renewal (P)      Tkm         7.00       5.930       07.00     1.00          14.28 %
             TRR(P)


             b)Through Sleepers Renewal      Tkm         5.00       4.920       7.00      1.870         26.71 %
             (P) TSR(P)

             c)Through Rail Renewal (S)
             TRR(S)                          Tkm         3.750      Nil         10.00     2.16          21.60 %

             d)Through Sleepers Renewal
             (S) TSR(S)                      Tkm         -          -           0.86      --            -


       2     Through Fitting Renewal - TFR  Tkm          45.00      18.80       168.00    12.65         7.52 %

             Through Fitting Renewal on
       3                                     Nos         -          -           204       30            14.70%
             Turnouts – TFR-T/O


             Through Weld Renewal -
       4                                     Tkm         10.00      2.520       2.00      --            -
             TWR

                                                                                                        7.7%
             Through Formation
       5                                     Tkm         31.00      7.910       20 (12)   1.54
             Treatment - TFTR
                                                                                                        ( 12.83%)

             Deep Screening of Plain
       6                                     Kms         40.00      81          80        65.300        81.65 %
             Track

       7     Deep screening of Points        Nos         105        55          105       15            14.28%