Page 4 - ENGINEERING
P. 4
2. Performance of track renewal works:
Progress
% of
Target
S. Target Progress 21-22 Progress
No Item Unit 2020-21 2020-21 2021- over target
22
(Upto 2021-22
22.10.21)
CTR
1 Track Renewal 7.88 5.425 12.43 2.515 20.23 %
Units
a)Through Rail Renewal (P) Tkm 7.00 5.930 07.00 1.00 14.28 %
TRR(P)
b)Through Sleepers Renewal Tkm 5.00 4.920 7.00 1.870 26.71 %
(P) TSR(P)
c)Through Rail Renewal (S)
TRR(S) Tkm 3.750 Nil 10.00 2.16 21.60 %
d)Through Sleepers Renewal
(S) TSR(S) Tkm - - 0.86 -- -
2 Through Fitting Renewal - TFR Tkm 45.00 18.80 168.00 12.65 7.52 %
Through Fitting Renewal on
3 Nos - - 204 30 14.70%
Turnouts – TFR-T/O
Through Weld Renewal -
4 Tkm 10.00 2.520 2.00 -- -
TWR
7.7%
Through Formation
5 Tkm 31.00 7.910 20 (12) 1.54
Treatment - TFTR
( 12.83%)
Deep Screening of Plain
6 Kms 40.00 81 80 65.300 81.65 %
Track
7 Deep screening of Points Nos 105 55 105 15 14.28%
Page 3 of 7