3. Track machine utilisation:
Target 2021- Progress up to
Sl No Type of Machine
22 Sept ’21
Tie Tamping 1400 Km 795.650 Km
1
Machine
2 Unimat 600 Pts 266 Pts
4. Level crossing works
2020-21 2021-22
Sl
No Description of item Boards Internal Progress Boards Internal Progress
Target Target Target Target
(22.10.21)
Construction of Road
1 - - - - - -
Over Bridge
Construction of Limited
2 10 12 14 09 21 03
Height Subways
Closure of Level
3 crossings on account of - - - - - -
diversion of Traffic
Closure of Level
4 crossings on account of - - - - - -
meager traffic