Page 39 - EOI_Wallace Bishop Retail Redevelopment
P. 39

IN FOCUS

          PALMWOODS HOTEL














          SJ Higgins Group was engaged to deliver a refurbishment of a 100   of the building prior to construction. A lack of information on the build-
          year old hotel.                                    ing including the design, how the structure was build and a lack of
                                                             documentation on existing services added to the challenges.
          The project was delivered over two stages including relocation and
          refurbishment of amenities, new bar and TAB facilities as well as the   After construction commenced, we discovered several latent condi-
          refurbishment of the dining area and beer garden. Delivery of this   tions including the flooring being substrate, which required significant
          refurbishment was staged to enable the hotel and pub to remain   additional works to ensure the floors were rebuilt to current standards.
          operational during construction.
                                                             Delivering a refurbishment project in a historic hotel that remained
          Scope of works                                     operational throughout the project lifecycle added to the complexity of
                                                             this project.
            ˃ Stage 1 works involved a deconstruction and gutting, relocation of
           amenities. As part of Stage 1 a new island bar was installed as well   Our project team met these challenges with meticulous planning.
           as new bifold doors, windows and new flooring.    Drawing on previous experience delivering complex projects, our site
                                                             team worked with the consultant to alter the architectural design to
            ˃ Stage 2 comprised rebuilding with outdoor beer garden roof struc-  ensure compliance with current construction standards.
           ture as well as a new stone meals orders counter and new flooring.
           In addition, the sports bar received a facelift, new flooring including
           an upgrade to technology.
              Project challenges

          As this is a 100 year old structure, the construction risks can be
          considerably higher as it was nearly impossible to determine the true
          project scope due to the difficulty to fully ascertain the true condition















































                                                                                                              39