IN FOCUS

          MACARTHUR CENTRAL FOOD COURT














          Several hours were spent obtaining and preparing timber samples for   Value adding
          the pergola ceiling for approval by the client including many visits to
          various timber yards to select a material that met both the structural   We worked in close partnership with our client from the outset in
          requirements of the ceilings as well as the finish the Client was after.   order to fully understand the project requirements and determine how
                                                              we could best maximise value.
          The challenge of floor covering works in a fully functional food court
          was overcome by breaking the 700m² area up into smaller sections to   Our team delivered a quality refurbishment project with no effect on
          ensure the existing floor covering could be removed and made safe   the operational activity of the shopping centre.
          by the time the centre opened every morning.        The alternative design proposal for the timber pergola ceiling resulted
                                                              in both time and cost savings.
                                                              The original design involved the installation of the large structural
                                                              steel members clad in a timber veneer. This proved almost impossible
                                                              to achieve given the height of the ceiling and the access to the area
                                                              from Ground Level via a boom lift. The final design saved approxi-
                                                              mately 30% in time and cost.