                                   Alameda Corridor–East Construction Authority

                                   4900 Rivergrade Road, Ste. 120 Irwindale, CA 91706 (626) 962-9292 fax (626) 472-0094 www.theaceproject.org
                             **CONSTRUCTION ALERT-UPDATE**

                   FULLERTON ROAD BETWEEN RAILROAD STREET AND
        ROWLAND STREET/SAN JOSE AVENUE TO CLOSE FOR 36 MONTHS;

                       LOCAL BUSINESS ACCESS WILL BE MAINTAINED

              NORTH FULLERTON ROAD CLOSURE                                     DETOUR ROUTES

                 ROWLAND ST.
                                                                                                     ROAD
                                                                                                   CLOSURE
               ROAD
             CLOSURE
              LOCAL
             ACCESS
               ONLY
                                                                                                               CHARLIE RD.

                                                                                                                    NOGLAES ST.



                                               GALE AVE.



                                                     NOT TO SCALE
                                                                 (Not to Scale)
     WHAT
     The  Alameda  Corridor-East  Construction  Authority  (ACE)  has  begun  construction  on  the  Fullerton  Road  Grade
     Separation  Project,  immediately  north  of  State  Route  60  in  the  City  of  Industry  and  unincorporated  community  of
     Rowland  Heights.  The  project  will  consist  of  a  six-lane  roadway  underpass  for  vehicular  traffic,  four-track  railroad
     bridge,  and  a  roadway  bridge  for  Railroad  Street  spanning  Fullerton  Road.  Upon  completion,  crossing  congestion,
     potential collisions with trains and noise from train horns will be eliminated. The next phase of work requires the full
     closure of Fullerton Rd. between Railroad St. and Rowland St./San Jose Ave. for utility relocation work and to build the
     underpass and bridges (see map above).
     WHEN
     Major construction will commence on Monday,  August  28,  2017  with the closure of Fullerton Rd. between Railroad
     St. and Rowland St./San Jose Ave. to through traffic for 36 months. Most work will take place on weekdays  between 7
     a.m.  and  4  p.m.  Weekend  and  night  work  will  be  performed  only  when  necessary.  Completion  of  construction  is
     anticipated in Summer 2020.
     WHAT TO EXPECT
     Northbound and southbound traffic lanes on Fullerton Rd. between Railroad St. and Rowland St./San Jose Ave. will be
     closed to through traffic. Access to local businesses on Fullerton Rd. will be maintained, from Rowland St./
     San  Jose  Ave. Motorists are encouraged to use Azusa Ave. and Nogales St. as major north-south detour routes. Gale
     Ave., Rowland St. and San Jose Ave. remain open for east-west travel. Portions of the adjacent sidewalks will also be
     closed with pedestrian detours provided. Motorists and pedestrians are urged to obey posted signs and exercise caution
     while in the vicinity of the construction activities.
                 Para información o preguntas, por favor llame al teléfono directo o visite el sitio web en:
                          如有疑問或需要索取工程最新資料,請致電輔助熱線或參閱工程網頁
                    For the most up-to-date information or questions, please call or visit:
                                 (888) ACE-1426 or www.theaceproject.org
                          Thank you for your patience and cooperation...At ACE, it’s Safety First!

                       Note: Construction is a dynamic process and information is subject to change without notice.   Rev 8/15/17
                                           Work activity is subject to weather conditions.