STELLAR PROJECT 3: Grabill Downtown Streetscape Improvement Project
Uses Quantity Unit Unit Cost Total
1 Mobilization and Demobilization (5%) 1 LS $19,900.00 $19,900
2 Maintenance of Traffic 1 LS $40,000.00 $40,000
3 Erosion Control 1 LS $10,000.00 $10,000
4 Construction Engineering 1 LS $10,000.00 $10,000
5 Clearing of Right Of Way 1 LS $8,000.00 $8,000
6 Common Excavation 160 CYS $45.00 $7,200
7 Concrete Removal 90 SYS $30.00 $2,700
8 Asphalt Pavement Removal (Full Depth) 605 SYS $45.00 $27,300
9 Asphalt Surface Milling (1” –2” Depth) 2,185 SYS $2.50 $5,500
10 Asphalt Surface Milling (3” –4” Depth) 200 SYS $4.50 $900
11 HMA Surface, Type B, 165#/Syd (1-1/2”) 120 TON $85.00 $10,200
12 HMA Surface, Type B, 330#/Syd (3”) 35 TON $75.00 $2,700
13 HMA Wedge & Level, Type B 80 TON $75.00 $6,000
14 Concrete Roadway Patch, 9-12” Depth, Match Existing (High Early) 235 SYS $125.00 $29,400
15 Decorative Brick (Roadway) 205 SYS $150.00 $30,800
16 Compacted Aggregate, #53, 12” Depth (For Roadway) 140 CYS $60.00 $8,400
17 Compacted Aggregate, #53, 6” Depth 40 CYS $60.00 $2,400
18 Concrete Pavement, 6” Depth (For Driveway) 70 SYS $100.00 $7,000
19 Concrete Curb, Type III 325 LF $50.00 $16,300
20 Decorative Brick (Sidewalk) 50 SYS $150.00 $7,500
21 Concrete Sidewalk, Remove and Replace, 4” Depth 395 SYS $85.00 $33,600
22 Curbface Sidewalk (Under Awning) 450 SYS $105.00 $47,300
23 Concrete Driveway, Remove & Replace, 6” Depth 60 SYS $85.00 $5,100
24 Concrete Sidewalk, 4” Depth 160 SYS $80.00 $12,800
25 ADA Curb Ramp 13 EA $2,500.00 $32,500