Page 120 - New Allen Alliance Digital Book
P. 120
STELLAR PROJECT 6: Monroeville Monroe Street Corridor
Gap: $730,270.00 Uses Quantity Unit Unit Cost Total Stellar (INDOT) Local Match
Leverage: $444,904.62
Excavation, Common 650.0 Cys $25.00 $16,250.00 $13,000.00 $3,250.00
Subgrade Treatment, Type II 450.0 Sys $40.00 $18,000.00 $14,400.00 $3,600.00
Milling, Asphalt, 1.5 IN. 7400.0 Sys $8.00 $59,200.00 $47,360.00 $11,840.00
HMA QC/QA, Type B, Surface 9.5 mm 552.0 Tons $100.00 $55,200.00 $44,160.00 $11,040.00
HMA Binder for Wedge and Leveling 245.0 Tons $80.00 $19,600.00 $15,680.00 $3,920.00
HMA for Approach, Type B 121.0 Tons $75.00 $9,075.00 $7,260.00 $1,815.00
HMA Patching, Type B 120.0 Tons $80.00 $9,600.00 $7,680.00 $1,920.00
Asphalt for Tack Coat 3.0 Tons $450.00 $1,350.00 $1,080.00 $270.00
Compacted Aggregate fo Base , No. 53 663.0 Tons $35.00 $23,205.00 $18,564.00 $4,641.00
Curb and Gutter, Concrete 4178.0 Lft $23.00 $96,094.00 $76,875.20 $19,218.80
Plain Cement Concrete Pavement, Approach, 6 inches 450.0 Sys $55.00 $24,750.00 $19,800.00 $4,950.00
Sidewalk, Concrete, 4 inches 2460.0 Sys $38.00 $93,480.00 $74,784.00 $18,696.00
Curb Ramp, Concrete 20.0 Each $500.00 $10,000.00 $8,000.00 $2,000.00
Plain Concrete Pavement, for Widening, 7 335.0 Sys $55.00 $18,425.00 $14,740.00 $3,685.00
Detectable Warning Surface 20.0 Each $125.00 $2,500.00 $2,000.00 $500.00
Sign, Sheet, Encap. Lens with Legend, 0.080 inches 70.0 Sft $25.00 $1,750.00 $1,400.00 $350.00
Sign Post, Square, 1, Reinforced Anchor Base 196.0 Lft $18.00 $3,528.00 $2,822.40 $705.60
Line, Thermo., Solid, Yellow, 4 inches 3580.0 Lft $1.00 $3,580.00 $2,864.00 $716.00
Transverse Markings, Thermo.., Stop Line, 24 inches 60.0 Lft $4.50 $270.00 $216.00 $54.00
Transverse Markings, Thermo., White, Crosswalk, 24 inches 630.0 Lft $4.00 $2,520.00 $2,016.00 $504.00
Construction Sign, Type B 8.0 Each $100.00 $800.00 $640.00 $160.00
Construction Sign, Type A 8.0 Each $200.00 $1,600.00 $1,280.00 $320.00
Barricade, Type III-B 24.0 Lft $15.00 $360.00 $288.00 $72.00
120