                   25   End Section, 15                                  1.0      Each        $470.00      $470.00
                   26   Inlet, J-10                                      4.0      Each       $2,500.00    $10,000.00
                   27   Inlet, E-7                                       7.0      Each       $2,100.00    $14,700.00
                   28   Casting, Furnish and Adjust to Grade             2.0      Each        $950.00     $1,900.00
                   29   Structure Backfill, Type 1                       375.0    Cys          $25.00     $9,375.00
                   30  Pipe Plug                                         2.0      Each        $500.00     $1,000.00
                   31  Core Hole in Structure                            1.0      Each        $150.00      $150.00
                   32   Fire Hydrant, Relocate                           10.0     Each       $4,500.00    $45,000.00
                   33  Clearing Right of Way (4%)                        1.0      LSum       $38,800.00    $38,800.00
                   34  Erosion Control (3%)                              1.0      LSum       $29,100.00    $29,100.00
                   35  Construction Engineering (5%)                     1.0      LSum       $48,400.00    $48,400.00
                   36  Maintenance of Traffic (3.5%)                     1.0      LSum       $29,100.00    $29,100.00
                   37  Mobilization and Demobilization (5%)              1.0      LSum       $48,400.00    $48,400.00
                      Construction Sub-Total                                                           $1,162,712.00


                   38  Engineering                                                                      $149,407.00
                   39  Environmental Review                                                              $25,000.00
                   40  R/W Engineering & Legals                                                          $32,500.00
                   41  Acquisition                                                                       $55,000.00
                   42  Grant Administration $ Labor Standards                                            $50,000.00
                   43  Inspection                                                                        $74,703.50
                      Non-Construction Sub-Total                                                        $386,610.50

                      Total Project Costs                                                              $1,549,322.50