Monroeville Monroe Street Corridor Improvement Project


                                      The Monroe Street project is located between Alliger Street and S.R. 101 (0.37   Readiness:
                                      miles).  Monroe Street is a local road consisting of two travel lanes with a parking   •   Listed as a Functionally Classified Road through INDOT.
                                      lane on both sides and 20 mph posted speed limit. It makes a direct connection   •   10% local match funding committed in addition to 100% of pre-construction
                                      between downtown and the community park entrance.           costs.
                                                                                                •   Preliminary engineering completed.
                    GRABILL           The proposed improvements include the following:          •   Rule 5 permit needed.
                                      •   Rehabilitation of the existing pavement by milling and resurfacing with HMA   •   Red flag survey completed, no significant environmental issues identified.
                                        pavement
                    HARLAN            •   Construction of new concrete curb and gutter on both side of the pavement
                                      •   Construction of new concrete 8-foot curb face sidewalk, 5-foot on west side and   Budget: $1,175,174
                                        new ADA curb ramps
                   HOAGLAND           •   Reconstruction of existing concrete drive approach    Funding Partners:
                                      •   Rehabilitation of the existing storm inlet, manhole structures and pipes  Town of Monroeville
                LEO-CEDARVILLE        •   Patching the existing asphalt pavement                Indiana Department of Transportation
                                      •   Maintaining on-street parking on onside of the road (west side)
                                      •   Installing new traffic sign and pavement markings
                 MONROEVILLE          •   Installing new decorative street lights

                                      Impact:
                  NEW HAVEN           •   Provides improved pedestrian connectivity, accessibility and safety in and
                                        between the Monroeville Community Park and the downtown
                                      •   Part of community-wide walkability improvements
                  WOODBURN            •   Improves infrastructure including sidewalks, roadway, streetlights and
                                        stormwater drainage
                                      •   Improves aesthetic appeal of a key corridor that links key community assets
                                      •   Implements recommendations from the Monroeville ADA Transition Plan and
                                        Strategy 6.5 of the New Allen Strategic Investment Plan, 2016.