Monroeville Monroe Street Corridor Improvement Project
The Monroe Street project is located between Alliger Street and S.R. 101 (0.37 Readiness:
miles). Monroe Street is a local road consisting of two travel lanes with a parking • Listed as a Functionally Classified Road through INDOT.
lane on both sides and 20 mph posted speed limit. It makes a direct connection • 10% local match funding committed in addition to 100% of pre-construction
between downtown and the community park entrance. costs.
• Preliminary engineering completed.
GRABILL The proposed improvements include the following: • Rule 5 permit needed.
• Rehabilitation of the existing pavement by milling and resurfacing with HMA • Red flag survey completed, no significant environmental issues identified.
pavement
HARLAN • Construction of new concrete curb and gutter on both side of the pavement
• Construction of new concrete 8-foot curb face sidewalk, 5-foot on west side and Budget: $1,175,174
new ADA curb ramps
HOAGLAND • Reconstruction of existing concrete drive approach Funding Partners:
• Rehabilitation of the existing storm inlet, manhole structures and pipes Town of Monroeville
LEO-CEDARVILLE • Patching the existing asphalt pavement Indiana Department of Transportation
• Maintaining on-street parking on onside of the road (west side)
• Installing new traffic sign and pavement markings
MONROEVILLE • Installing new decorative street lights
Impact:
NEW HAVEN • Provides improved pedestrian connectivity, accessibility and safety in and
between the Monroeville Community Park and the downtown
• Part of community-wide walkability improvements
WOODBURN • Improves infrastructure including sidewalks, roadway, streetlights and
stormwater drainage
• Improves aesthetic appeal of a key corridor that links key community assets
• Implements recommendations from the Monroeville ADA Transition Plan and
Strategy 6.5 of the New Allen Strategic Investment Plan, 2016.
74