Page 19 - Green Builder's Resilient Housing Design Guide 2018
P. 19

CREDIT: NATIONAL GUARD





















































            Preparing for the worst. Changing weather patterns are making scenes like this Hurricane Harvey-related one all-too-common nationwide. They’re
            also a signal flare for builders, who need to prepare even more for natural disasters.

             7     Improper elevation of habitable space and utilities relative to flood risks
                   resulted in structural and contents damage.

                    LEVATED  HOMES TEND  to survive flooding much    Bottom line: The depth is key. It should be noted, however, that
                    better than those on low-lying foundations. Flood vents   pilings do not guarantee an unscathed structure after a storm:
                    in elevated reinforced block or monolithic foundations   “A study of Topsail Island found that 98 percent of post-1986
                    can save a home, if flood levels adhere to “normal” levels.   oceanfront houses (200 of 205) remained after the hurricane.
            E But let’s assume future storm surges WILL exceed current   Ninety-two percent of the total displayed no significant damage
            height estimates—and focus on the use of pilings.       to the integrity of the piling foundation. However, 5 percent were
              After Hurricane Fran in 1996, FEMA conducted a study of what   found to have leaning.”
            happened to stilt homes. The agency found that:          FEMA tested the leaning buildings to find out what happened.
              “A significant reduction in building losses was observed in simi-  They discovered that among the leaning buildings, “none of the
            larly sized oceanfront buildings constructed after the North Caro-  leaning pilings tested met the required piling embedment standard.
            lina Building Code was amended in 1986 to require a minimum   Many were much shorter.”
            embedment to 5 feet National Geodetic Vertical Datum (NGVD),   In other words, the contractors failed. Out of this research, the
            or 16 feet below the original ground elevation, whichever is shal-  suggestion was made that pilings be embedded to a minimum depth
            lower, for pilings near the ocean.”                     of 10 feet NGVD, without exception.


            www.greenbuildermedia.com                                      Resilient Housing Design Guide GREEN BUILDER MEDIA  19
   14   15   16   17   18   19   20   21   22   23   24