Khun Chitcherd Praditsuk Tel. 0 2575 2600


                       ▪  Huawei Technologies (Thailand) Co., Ltd. – CAT CDMA Project, Phase 2
                            (OSP-Optical Fiber Transmission- Survey and Design)

                          ▪  Routing Survey
                          ▪  Engineering Design
                          ▪  Permission Application
                          ▪  Work Period May 2006 – July 2006
                          ▪  Contract Value : as requested
                          ▪  Customer Rep.
                                      Khun Chitcherd Praditsuk
                                           Tel. 0 2575 2600

                       ▪  Huawei Technologies (Thailand) Co., Ltd. – CAT CDMA Project, Phase 2
                            (OSP-Optical Fiber Transmission- Installation)

                          ▪  Installation of over 500 KM of Optical Fibre Cable for 100 links
                          ▪  Commissioning of all installed network
                          ▪  Work Period June 2006 – Jan 2007
                          ▪  Contract Value : as requested
                          ▪  Customer Rep.
                                      Khun Chitcherd Praditsuk
                                           Tel. 0 2575 2600

                       ▪  TOT Corporation Public Co., Ltd. ,  Installation of STM 16 and Optical
                           Fiber in Chiang Rai Project

                          ▪  Engineering Design
                          ▪  Installation of OFC Cable for SDH Network 3 Links
                          ▪  Commissioning Test all installed network
                          ▪  Work Period : March 2006 – Nov 2006
                          ▪  Contract Value : as requested

                       ▪  TOT Corporation Public Co., Ltd. ,  Installation of Optical Fiber for 125
                           MCAB ( 11 K ) in Metro Area 4 Bangkok Project

                          ▪  Engineering Design
                          ▪  Installation of OFC Cable for approx. 127 KM
                          ▪  Commissioning Test all installed network
                          ▪  Work Period : Nov 2010 – July 2011
                          ▪  Contract Value : as requested