Page 27 - EPC Solution
P. 27

Wireless and IT Network


                        ▪  Bellwater (Thailand) Limited. – TA Orange Co., Ltd. , Nationwide Cell
                           Site Installation

                          ▪  Site Survey includes General Arrangement Drawing (GAD)
                          ▪  Engineering Design for Site Preparation
                          ▪  Detailed Drawing Design (DDD) and Document Package
                          ▪  Permission Application
                          ▪  Site Preparation includes Site Clearing, Tower Foundation,
                              Container Foundation, Piling, Fencing and etc.
                          ▪  Tower Erection includes Painting, Grounding, Lighting Protection ,
                              OB Light Installation
                          ▪  Electrical Work for Base Station
                          ▪  Preparation Documentation for Customer Physical Check
                          ▪  Certified Engineer signed in document where required
                          ▪  Work Period Feb 2002 – July 2002
                          ▪  Customer Rep.
                                        Khun Graham Smith
                                                  Tel. 0 1810 2056

                        ▪  Rohn Products International (Thailand) Co., Ltd. - TA Orange Co.,
                           Ltd., Nationwide Cell Site Installation

                          ▪  Site Survey includes General Arrangement Drawing (GAD)
                          ▪  Engineering Design for Site Preparation
                          ▪  Detailed Drawing Design (DDD) and Document Package
                          ▪  Permission Application
                          ▪  Site Preparation includes Site Clearing, Tower Foundation,
                              Container Foundation, Piling, Fencing and etc.
                          ▪  Tower Erection includes Painting, Grounding, Lighting Protection,
                              OB Light Installation
                          ▪  Electrical Work for Base Station
                          ▪  Preparation Documentation for Customer Physical Check
                          ▪  Certified Engineer signed in document where required
                          ▪  Work Period June 2002 – November 2002
                          ▪  Customer Rep.
                                        Khun Micheal Holmes
                                        Tel. 0 1841 9342


                        ▪  The Leighton Limited – Equipment and Tower Dismantling Works to
                          BFKT sites in Bangkok








                   January 2021                                                                     Page 27 of 37
   22   23   24   25   26   27   28   29   30   31   32