Page 114 - Civil Engineering Project Management, Fourth Edition
P. 114
The resident engineer’s duties
undertaking hand augering of the foundation site or, if necessary, using the
contingency money under the contract to instruct the contractor to excavate
a trial hole paid under dayworks (see Sections 13.8 and 16.3).
9.5 Some important points the resident engineer 99
should watch
Some important provisions of the ICE conditions of contract that need to be
borne in mind by the RE are as follows:
1. All instructions to the contractor have to be given in writing or, if given
orally, have to be confirmed in writing ‘as soon as is possible under the
circumstances’ (Clause 2(6)(b)).
2. If the contractor receives an oral instruction and confirms it in writing, and
the engineer does not contradict such confirmation ‘forthwith’, then the
confirmation is ‘deemed an instruction in writing by the engineer’ (Clause
2(6)(b)). These confirmations of verbal instructions – or ‘CVIs’ as they are
called – can raise special difficulties for the RE and the problems of hand-
ling them are dealt with in detail in Sections 13.3 and 17.6.
3. Although an RE may not have been delegated powers to decide how much
should be paid (if anything) against a contractor’s claim for extra payment,
he has powers to write to the contractor stating his views on the claim. It is
imperative he should do so, in each case, so that the facts as he sees them
are on record.
4. There are numerous ‘time clauses’ in the conditions of contract, that is,
clauses stipulating some time limit within which the engineer (and therefore
probably the RE also) must take action. An important instance is the require-
ment that the engineer must comment on the contractor’s proposed pro-
gramme within 21 days of its receipt, otherwise the engineer is deemed
to have accepted it (Clause 14(2)). The same, in effect, applies to any part-
programme or revised programme the contractor supplies. Consequently if
the engineer fails to comment within 21 days, the contractor’s programme is
deemed approved and anomalies may be introduced if the programme does
not reflect the specified timing.
5. The RE has to ensure that the contractor receives all approvals, drawings,
details and other information he needs to construct the works, in good
time; otherwise the contractor may claim for delay (Clause 7(4)).
6. The RE should not accept lower grade materials or workmanship than that
specified, even if the contractor offers a lower rate of charge than the bill
rate for the specified material, unless the engineer agrees to this. Such a
change is a variation requiring issue of a VO.
7. The RE must give immediate notice to the contractor when any defects in
materials or workmanship are observed, because it may be very difficult to
rectify a defective part of the work after it is completed. Hence inspections