Page 113 - Civil Engineering Project Management, Fourth Edition
P. 113

Civil Engineering Project Management
                          98
                          • Examining all claims from the contractor, preparing data relevant to such
                             claims, sending to the contractor an initial response to every such claim.
                          • Reviewing dayworks sheets, increase of prices, and all other matters requir-
                             ing accountancy checking.
                          • Checking the design of contractor’s temporary works for compliance with
                             safety regulations and satisfactory construction of permanent works.
                          • Acting as the engineer’s Safety Supervisor on site (see Section 9.6).
                          • Reporting on all the foregoing to the engineer in the form he requires.
                          9.4 Some common problems


                          The following are typical of some common problems the resident engineer –
                          frequently referred to as ‘the RE’ below – may have to deal with.
                          1. The contractor will not undertake some variation of the work the RE orders
                             unless he receives a VO signed by the engineer in advance. This usually
                             means the contractor wants to know in advance what he will be paid for the
                             varied work. In most cases the RE should have enough experience to advise
                             how the varied work will be paid for. The contractor is, however obliged to
                             carry out such work as instructed and the engineer will have to issue a VO
                             stating the pay rates to be applied as determined by the contract.
                          2. The contractor claims that the RE’s clarification of the details of some work
                             varies that work and entitles him to extra payment, but the RE decides no
                             payment should be made. If the contractor continues in his claim, the RE
                             should forward it to the engineer with details, forewarning the contractor
                             that if the engineer agrees no payment is due, the contractor will have to
                             decide if he will take the matter to adjudication.
                          3. The RE approves some material, workmanship or method of working
                             of the contractor, but later finds the engineer thinks the RE’s approval was
                             wrong. If the error is one which the engineer feels he must rectify, he must
                             do so by negotiation with the contractor, if necessary agreeing some extra
                             payment to the contractor for abortive work. But, if the engineer suspects
                             the contractor has taken advantage of the RE’s failure to appreciate the con-
                             sequences of the contractor’s proposal, or has concealed such consequences
                             from the RE, he may decide to countermand the resident RE’s decision
                             without agreeing any recompense to the contractor.
                          4. A problem frequently occurring is when the RE has to consider whether
                             some excavation for a foundation has reached satisfactory foundation mater-
                             ial. The problem can be compounded by the fact that to refer it to the engin-
                             eer may cause a delay to the job, giving the contractor reason to make a
                             delay claim. But, if the RE is in doubt as to whether the material is satisfac-
                             tory he must refer the matter to the engineer (or his geotechnical adviser).
                             However, the RE should have foreseen the problem and taken steps in good
                             time to investigate what the ground conditions are likely to be, either by
   108   109   110   111   112   113   114   115   116   117   118