Page 140 - Civil Engineering Project Management, Fourth Edition
P. 140

125
                                                               Starting the construction work
                          11.5 Some early tasks for the resident engineer
                          At the end of the first week the resident engineer will no doubt find that he
                          already has a number of tasks to do. If bulk excavation is about to start it will be
                          essential to take levels of the natural ground over the site where the excavation
                          is to take place, if these levels are not already available in sufficient detail. This
                          is urgent work, for there will be no chance later of finding what the natural
                          ground levels were and the calculations for quantities of excavation would then
                          be largely ‘intelligent guesswork’ or agreement will have to be sought on bill
                          quantities, which may differ from the true quantity excavated. If the contractor
                          has taken his own levels over the site and the resident engineer has let pass the
                          opportunity of checking them, he will be in no position to argue against the
                          contractor’s figure for the excavation.
                            It may not be sufficient to rely on ground levels shown on the contract draw-
                          ings because these may be based on interpolation of published contoured maps
                          of the area. Where such contours originate from aerial photography they can be
                          a metre in error because they may reflect the top of vegetation rather than the
                          soil level.
                            Another early task is to carry out and agree with the contractor the state of
                          existing buildings which might be affected by construction of the contract works,
                          and the state of approach roads to the site. This is essential so that any claims
                          for compensation for damage can be decided properly. In this survey sets of
                          photographs of existing cracks or damage, as well as general views, form an
                          important part.
                            The resident engineer must see that all  productive top-soil is stripped and
                          stacked separately for later re-use. All amounts of soil should be so stacked,
                          even that taken off areas for the site offices, since there is often a lack of soil
                          at the end of the job. The question of disposal of excavated material will have
                          to be considered. In many countries there is now increasing control over what
                          materials may be disposed of to landfill and these need to be borne in mind
                          when agreeing with the contractor what to do with unwanted excavated
                          materials.
                            The next task the resident engineer may need to do, if he has not done it
                          already, is to check the delivery times for any equipment or materials to be sup-
                          plied under other contracts or by the employer, such as the supply of pipes and
                          valves. On overseas jobs there may be many separate contracts for the supply
                          of materials. All these separate supply contracts have to be checked in detail
                          to ensure that nothing has been missed.



                          11.6 Meeting the employer


                          Shortly after his arrival on site the resident engineer should see if the employer
                          wishes to meet him and will set aside a morning or afternoon for going over
   135   136   137   138   139   140   141   142   143   144   145