Page 41 - Civil Engineering Project Management, Fourth Edition
P. 41

Civil Engineering Project Management
                          26
                          Thus problems can occur if faulty performance is partly due to conditions
                          arising which are not covered by the promoter’s specification.
                            Where a DBO contract is let on the basis that the contractor also finances the
                          project, associating with a bank for the provision of the necessary funds, the
                          operating period may then be long term, for 15–20 years or more. This is
                          typically a Private Finance Initiative (PFI) project, described in Section 1.7.
                          The risks on the contractor are then increased since they include a substantial
                          dependency on the terms of the income he is to receive. The promoter has the
                          cost of setting up a long-term supervisory system to cover the operation
                          period and may face the risk of circumstances arising which are not covered
                          in the original contract.
                          (c) Engineer, procure and construct contracts


                          An engineer, procure and construct (EPC) contract is a form of D&B contract
                          under which a design engineer or firm of design consultants heads a team
                          which includes an experienced contractor and perhaps a plant supplier. The
                          promoter specifies his project requirements in outline which the team designs
                          in detail in continued liaison with him. The EPC organization arranges and
                          manages construction, letting specialist work packages out as necessary to
                          suitable sub-contractors. The promoter pays the actual cost of the work plus a
                          fee, subject to a guaranteed maximum price, or to a target cost with an arrange-
                          ment for the sharing of savings or excess costs on the target.


                          (d) Partnering


                          Details of partnering are given in Section 1.9. There are two types: ‘term (or full)
                          partnering’ which covers an intention to carry out a series of projects together
                          or for a given period; and ‘project-specific partnering’, i.e. co-operation for one
                          job at a time.
                            Normally a promoter negotiates a partnering agreement with his consultant
                          (if he employs one) and a contractor of his own choosing, usually because of
                          past satisfactory experience of working with him. If competitive tendering is
                          required, then a selected list of contractors may be invited to bid – on the basis
                          of experience, quality of staff available, and costs plus charges for overheads
                          and profit, etc. (similar to cost reimbursement contracts outlined in Section 1.3).
                          But if open competitive tendering is used, the advantage of basing a partnering
                          agreement on past successful working with a contractor may be lost.


                          (e) ‘Term’ or ‘Serial’ contracting


                          This comprises letting an ordinary construction contract for carrying out a
                          series of works of an identical nature – re-surfacing roads, for example – for a
   36   37   38   39   40   41   42   43   44   45   46