Page 45 - Civil Engineering Project Management, Fourth Edition
P. 45

Civil Engineering Project Management
                          30
                          Table 3.1
                                                                  Disadvantages to employer
                          Advantages to employer Comparison of different methods of payment
                                                     – Re-measurement –
                          Greater certainty in pricing            Detailed bills of quantities needed
                          Project cost known with reasonable      Employer must meet extra costs due to
                           certainty                               changes
                          Facilitates valuation of variations     Work done has to be measured
                                                        – Lump sum –
                          Firm price known early                  Bid risks high hence tendered prices
                          Financial bids easily evaluated          may be high
                          Payment terms simple                    Long tender time required
                                                                  Variations difficult to value and agree
                                                 – Reimbursable with fixed fee –
                          Reduced documentation for tender        Bid evaluation difficult
                          Short tender time                       Price competition minimal
                          Variations easily evaluated             Checking and auditing contractor’s
                          Cost of project can be controlled        costs necessary
                          Methods of construction can be          No firm final cost
                           controlled by designer                 Contractor has no financial incentive
                          Design can be altered during             to minimize costs
                           construction                           Risk of inefficient contractor
                                                – Reimbursable with target cost –
                                        (as for reimbursable with fixed fee with following changes)
                          Contractor has financial motive         Target difficult to define initially
                           to be efficient                        Target may need changing owing to
                          Contractor shoulders some proportion of  changes in work required
                           cost exceeding target                  Disputes possible about fair target




                          Section 1.2. Where additional work is required, the contractor is paid for it at
                          ‘bill rates’ or, if different work is required, this is paid at similar or agreed
                          rates. Table 3.1 compares this method with the methods which follow.
                            The advantages are that the contractor can be paid fairly for the amount
                          of work he has to do, and the employer only has to pay for work actually
                          required, without having to pay a premium to the contractor for the risk of
                          undertaking, at his own cost, extra work due to quantity changes. Thus if no
                          major unforeseen conditions are encountered and the employer orders no
                          extra work, the cost of the job to the employer will come very near the original
                          sum tendered.
                            The use of bills of quantities has been the normal method of payment in
                          standard forms of contract for many years. This method is particularly effect-
                          ive where the employer wishes to control the design, or has the works largely
                          designed before going out to tender. With the works clearly defined, and
                          a fair system of measurement, the contractor’s risks are reduced and pricing
                          may be keen.
   40   41   42   43   44   45   46   47   48   49   50