Page 50 - Civil Engineering Project Management, Fourth Edition
P. 50

35
                                         Payment arrangements, risks and project cost estimating
                          3.3 Contractual risks arising during construction
                          Among the most common risks encountered during the construction of a pro-
                          ject by a civil engineering contractor under a standard type of construction
                          contract, are the following:
                          1. Design errors, quantification errors.
                          2. Design changes found necessary, or required by the employer.
                          3. Unforeseen physical conditions or artificial obstructions.
                          4. Unforeseen price rises in labour, materials or plant.
                          5. Theft or damage to the works, or materials and equipment on site.
                          6. Weather conditions, including floods or excessive hot weather.
                          7. Delay or inability to obtain materials or equipment required.
                          8. Inability to get the amount or quality of labour required, or labour strikes.
                          9. Errors in pricing by the contractor.
                          Most standard conditions of contract apportion the normal risks of construc-
                          tion to the party best able to control the risk. The apportionment will vary
                          from form to form but many have been agreed within the industry as giving
                          a reasonable balance between employer and contractor and it is generally
                          unwise to upset this for normal types of civil engineering work.
                            Thus under the ICE conditions of contract using a bill of quantities, risks 1,
                          2 and 3 are carried by the employer. Design changes can cause much extra
                          work, cost and delay to a contractor but may be forced on an employer by cir-
                          cumstances outside his control. To safeguard his position, an employer should
                          not enter unsuitable contracts which do not give him power to adopt reason-
                          able design changes at reasonable cost.
                            Risk 4 is usually carried by the contractor in times of low inflation.
                            Risk 5 is carried by the contractor who has to insure against it, although the
                          employer may also insure against consequent damage to works he owns, and
                          to any new works he takes over.
                            Risk 6, delay due to weather conditions, has traditionally been a con-
                          tractor’s risk and this has posed many problems for contractors because the
                          effect of inclement weather (mostly wet weather in the UK) can vary according
                          to the type of work undertaken. Any form of earth or road construction can be
                          severely affected by wet weather, whereas much building work need not be
                          so affected. The ICE standard conditions entitle a contractor to an extension
                          of the contract period for ‘exceptional adverse weather conditions’ but do not
                          authorize additional payment on account of it. The ICE ‘Engineering and
                          Construction Contract’ referred to in Section 4.2(f) attempts to define ‘excep-
                          tional weather conditions’ as a basis for claim, and allows time and payment
                          if these are exceeded.
                            Risk 7, delay in obtaining materials, is carried by the contractor in most cases,
                          except where the employer stipulates in the contract that a specific supplier shall
                          be used, when liability for delay may lie with the employer (see Section 14.2).
   45   46   47   48   49   50   51   52   53   54   55