Page 52 - Civil Engineering Project Management, Fourth Edition
P. 52

37
                                         Payment arrangements, risks and project cost estimating
                          The reference costs need to be accompanied by data, such as project size, pro-
                          ject components and distinctive features, dates of construction, and whether
                          the price includes land, legal and engineering costs. Inflation factors may
                          have to be applied to update the costs. By comparing the principal features of
                          the proposed project with those for which past costs are available, a probable
                          order of magnitude total cost may be derived.
                            The second method is the most reliable. Even before a feasibility study is
                          undertaken it should be possible to sketch out the proposed project on some
                          notional site if the actual site is not yet decided, so the layout and sizes of the
                          various components required can be judged. The components can be roughly
                          sized so that their possible cost can be estimated by comparison with price
                          data held for similar structures. This procedure can also reveal costs for items
                          which might otherwise have been missed.
                            The third method, using published cost curves, is not very reliable, because
                          the data on which such curves are based is so frequently absent, and virtually
                          every civil engineering project has some unique feature substantially affecting
                          its cost. Hence costs expressed per unit of size or output can vary greatly.
                          However, a cost curve can be used to show whether costs developed by the
                          other methods seem realistic.
                            While any of the above methods will involve uncertainty, they can be useful
                          in comparing different options for a scheme, provided uniform parameters are
                          used. The final estimate of cost drawn up by the engineer should be based on
                          current prices and include a substantial contingency sum. It need not include
                          for possible future inflation of prices, because this is a matter for the employer’s
                          financial advisers to deal with, but the basis of the estimate should be clear. The
                          possible range of the cost should be shown; but whether the employer chooses
                          to quote the highest or lowest estimate is up to him. Many a major project
                          providing a major benefit (including the Channel Tunnel) would probably not
                          have been built if the initial estimate quoted for it by the employer had not erred
                          on the optimistic side.



                          3.5 Estimating the cost of a project at design stage


                          As the design of a project is developed a more accurate estimate of cost is
                          possible, based on cost parameters derived from analysis of recent priced
                          contracts for similar work. The designs should show the layout and sizes of
                          component works required. For each such component it should be possible
                          to make an approximate estimate of the quantities of the key structural oper-
                          ations required, such as bulk excavation, main concrete in framework and
                          floors, wall areas, and roof areas. Examination of recent priced contracts can
                          then produce cost parameters that can be applied to the estimated quantities
                          for the proposed structure.
                            For example, using a past priced contract, the total concrete costs (inclusive
                          of formwork, reinforcement, finishes, joints, etc.) can be divided by the volume
   47   48   49   50   51   52   53   54   55   56   57