Page 47 - Civil Engineering Project Management, Fourth Edition
P. 47

Civil Engineering Project Management
                          32
                          definition of which costs will be reimbursed and which will not. Examples
                          of possible wording to achieve this are given in the IChemE ‘Green Book’ con-
                          ditions (see Section 4.5), and in the Schedule of Cost Components included
                          in the ICE ‘Engineering and Construction Contract’ (see Section 4.2(f)). Care
                          must be taken to ensure the wording adopted is clear. For complex works it
                          may be necessary to carry out a risk assessment to identify potential problems
                          and allocate the risks to either party.
                          (e) Target contracts
                          These are usually cost reimbursement contracts as (d) above, but with an esti-
                          mated target cost set for the works cost, and a fixed or percentage fee for
                          the contractor’s head office overheads and profit. If the contractor’s expenditure
                          exceeds the target he has to bear a proportion of the excess; if his expenditure is
                          less than target he receives a proportion of the difference as a bonus. Thus
                          there is a financial incentive to the contractor to be efficient and save costs.
                            But setting a fair target price can be difficult, and impossible if the amount
                          of work to be done is unpredictable. If a target has to be revised, a dispute
                          may arise between employer and contractor as to what the new target should
                          be; this defeats the purpose of this type of contract. If the work is reasonably
                          well defined, then a measurement contract is usually suitable. Consequently a
                          target price contract is not appropriate for many jobs.
                            If the initial target is set as a result of competitive tendering, then the
                          employer may feel some assurance that he is obtaining ‘value for money’. But
                          if the target is negotiated or later has to be varied, then the employer may feel
                          that the contractor’s knowledge of his intended methods and costs may
                          enable him to add a margin in the target estimate to safeguard his position.
                          This means that it is improbable that the target cost will ever be lower than the
                          contractor’s privately estimated bottom line price.


                          (f) Payment under design, build and operate contracts


                          Arrangements for payment under design, build and operate (DBO) contracts
                          may be partly direct and partly by income derived from the project operation as
                          described in Section 2.6(b).



                          3.2 Other payment provisions


                          (a) Price variation provisions


                          In times of inflation it may be advisable to include clauses within the contract
                          which set out how the contractor is to be reimbursed his extra costs due to any
   42   43   44   45   46   47   48   49   50   51   52