Page 51 - Civil Engineering Project Management, Fourth Edition
P. 51

Civil Engineering Project Management
                          36
                            Risk 8, failure to get labour, is usually shouldered by the contractor, mainly
                          because this lies within the ability of the contractor to control, and not the
                          employer.
                            Usually any requirement that the contractor should shoulder all or most
                          risks arises because the employer prefers to have a fixed financial commit-
                          ment, or because he has only a limited allocation of funds which he has
                          no authority to exceed. Some overseas governments will not authorize any
                          expenditure above the tendered sum. This fixing of the price and placing all
                          or most of the risks on the contractor can be expected to lead to generally high
                          prices. Also if unexpected circumstances occur which the contractor has not
                          allowed for, he may tend to adopt ‘short-cut’ methods which do not produce
                          the most satisfactory work, or he may be forced to finish the work at a loss.
                            For complex projects, and perhaps where major cost reimbursement or target
                          cost projects are envisaged, a formal risk assessment may be necessary in which
                          a risk register is set up, defining how each risk is to be dealt with and which
                          party is to carry the liability should the risk occur. In summary this may involve:
                          • identification of risks likely to arise by discussion between all interested
                             parties involved;
                          • analysis of each risk as to likely frequency, severity of impact on cost and
                             delay, both maximum and minimum;
                          • identification as to who is best able to manage the risk and/or who should
                             carry the costs which may arise;
                          • definition of risks falling on the contractor so that he can include for them
                             in his prices or insure against them.

                          The analysis of risks may be accompanied by a mathematical probability
                          exercise to try to assess the most likely outcome for the employer’s financial
                          planning purposes. As a general principle, it is usually best not to pass to the
                          contractor risks which are most difficult to assess as regards likelihood or cost,
                          since a contractor may then need to increase his price substantially to protect
                          his position, causing the employer to pay for a risk which may never arise.


                          3.4 Producing an initial cost-estimate of a project


                          At an early stage an employer will want to know the probable cost of his
                          intended project. Usually no realistic figure is possible until a feasibility study
                          of the project has been completed; before that only an ‘order of magnitude’
                          figure or ‘budget estimate’ can normally be quoted. Three main methods of
                          producing this are as follows:
                          • by reference to the cost of similar projects;
                          • by sketch layout and component costing;
                          • by use of cost curves if available.
                          The first assumes a record is available of the cost of past projects undertaken
                          by the employer’s engineer, or perhaps costs taken from the technical press.
   46   47   48   49   50   51   52   53   54   55   56