Page 48 - Puret Sound Energy Hand Book 1218
P. 48

Chapter 4


               Figure 22         Typical joint utility trench with primary voltage cable on your private property
                                  (cross-section view)


                           PRIMARY POWER CABLE                                    PRIMARY POWER CABLE
                   DIRECT BURIED OR DB120 CONDUIT INSTALLATION                SCHEDULE 40 CONDUIT INSTALLATION
                                                                                          18"
                              18"
                 ROADSIDE   TYPICAL     24" MIN                             ROADSIDE    TYPICAL      24" MIN
                 FINAL GRADE        TO EXCAVATED DIRT PILE                  FINAL GRADE          TO EXCAVATED DIRT PILE
                                         BACKFILL FOR DB120
                   36"                   CONDUIT/DIRECT BURIED
                   MIN       12" MIN     CABLE (NO ROCKS OVER                36"
                  COVER    SEPARATION    10" DIAMETER)                       MIN                   BACKFILL FOR
                                                                            COVER      12" MIN     SCHEDULE 40 CONDUIT
                48"                                                       48"         SEPARATION   (NO ROCKS OVER 10"
                                                                                                   DIAMETER)
               MAX                        6" OR 12" OF SAND, 5/8" MINUS,   MAX
                                          OR CLEAN BACKFILL SHADING  1
                                       3" OF SAND, 5/8" MINUS, OR CLEAN BACKFILL BEDDING

                   PHONE & TV       PRIMARY POWER CABLE DIRECTLY              PHONE & TV      PRIMARY POWER CABLE
                                                                                              IN CUSTOMER-PROVIDED
                                    BURIED OR IN PSE-PROVIDED GRAY                            DISCONTINUOUS GRAY
                                    DB120 GRADE CONDUIT                                       SCHEDULE 40 CONDUIT

                                     PRIMARY POWER, MAINLINE GAS, AND COMMUNICATIONS


                                               32"
                             ROADSIDE         TYPICAL        24" MIN
                             FINAL GRADE  POWER, GAS, AND COMMUNICATIONS  EXCAVATED
                                                                         DIRT PILE
                                             12" MIN        BACKFILL (NO ROCKS OVER 10" DIAMETER)
                               36" MIN     SEPARATION
                            48"   COVER   12" MIN   12" MIN
                            MAX          SEPARATION  SEPARATION  6" OR 12" MIN SAND SHADING AFTER COMPACTION  2


                                                            4" SAND BEDDING
                                                                                 1  SEE TRENCH AND BACKFILL REQUIREMENTS FOR
                                                                                  PRIMARY ELECTRIC LINE EXTENSION TRENCHES
                                                                                  (NO PSE GAS) ON PAGE 40.
                                    GAS                 PRIMARY POWER            2
                                     COMMUNICATIONS     CABLES OR CONDUIT         SEE TRENCH AND BACKFILL REQUIREMENTS FOR
                                                                                  PRIMARY ELECTRIC LINE EXTENSION TRENCHES
                                                                                  (WITH PSE GAS) ON PAGE 41.