Chapter 4



              Trench                The following requirements for the trench must be met before power conduits/cables
              excavating            will be installed.
              requirements          •   When you trench in a right-of-way on PSE’s behalf, the governing jurisdictions
                                        issue public roadway use permits to PSE.
                                    •   For trench work provided by you within a public right-of-way or a PSE easement,
                                        PSE requires that you use a Washington State licensed and bonded contractor
                                        and complete and sign a PSE trenching agreement form.
                                    •   Trench work within a public right-of-way must meet the erosion and sediment
                                        control requirements of the local jurisdiction.
                                       NOTE: Acquiring permits for excavation-related activity can take up to a month
                                       or longer depending on the amount of material being excavated, location of the
                                       excavation, and the jurisdiction issuing the permit. To avoid schedule delays, contact
                                       your PSE Project Manager for an estimated time frame to acquiring your permits.
                                    •   Provide a signed Excavation Requirements & Final Grade Certification document
                                        supplied by your Project Manager or PSE Representative.
                                    •   The trench shall be excavated according to the trench detail and PSE’s work
                                        sketch.
                                    •   The trench shall be straight and the trench bottom shall be smooth, level, and
                                        free from obstructions, sharp objects, or rocks larger than 1/2 inch in diameter.
                                    •   Excavated or loose material shall be placed at least 2 feet from the field edge of
                                        the trench.
                                    •   Water shall be removed by pumping or draining following the erosion and
                                        sediment control requirements of the local jurisdiction.
                                    NOTE: Trenches or vault excavations that are 4-feet-deep or greater require special
                                    sloping. Contact your PSE Project Manager for these requirements.


              Trench and            PSE will not energize its facilities until backfill is completed.
              backfill              When PSE primary cables are directly buried, or installed in PSE-provided gray
              requirements          DB120 grade conduit, you are responsible for the following:
              for primary
              electric line         •   Providing a minimum 3-inch bedding layer of sand, 5/8-inch minus, or clean
              extension                 backfill (with rocks or solid material no larger than 5/8 inch in diameter and no
              trenches (no              sharp objects) placed below cables/conduits.
              PSE gas)              •   A 12-inch layer of the same shading material above the directly buried cables/
                                        conduits.
                                    •   If native backfill is completely free of foreign objects and rocks in excess of
                                        8 inches in diameter, shading with sand, 5/8-inch minus, or clean backfill can be
                                        reduced to 6 inches.
                                    •   The remaining trench shall be backfilled with soil that is free of rocks larger than
                                        10 inches in diameter and foreign objects.
                                    When PSE primary cables are installed in gray Schedule 40 grade or better conduit,
                                    you are responsible for the following:
                                    •   Backfilling the trench with soil that is free of foreign objects and rocks larger than
                                        10 inches in diameter. Bedding and shading of the conduit with sand, 5/8-inch
                                        minus, or clean backfill is not required.