Chapter 5
Meter installation
This chapter provides you with PSE’s requirements for the metering equipment that you
must provide to hook up your new service. Please follow these requirements to avoid a
delay in your service hookup. If you have any questions about this information, call your
Customer Construction Services (CCS) Representative.
Service rating options
PSE’s metering equipment requirements for single-family residential structures (not
apartments or condominiums) are based upon the following single-phase service
ratings:
Voltage Ampere rating
120/240 200 A
120/240 400 A
120/240 over 400 A *
* If you need a three-phase service, please contact your CCS Representative. Such
services require the approval of PSE’s Meter Department and are not covered in this
handbook.
Responsibilities
Puget Sound
Energy PSE is responsible for installing the meter, service line, and current transformers (CTs).
Customer You are responsible for providing and installing all service entrance equipment (including
the meter base/socket and current transformer CT enclosure).