METODO PUNTO ALTO Y BAJO
 X  Y

 HORAS DE MANO DE OBRA  COSTOS DE PRODUCCION COSTO VARIABLE  COSTO FIJO
 9000 $                              51,750.00 $             40,500.00 $   11,250.00

 8000 $                              47,250.00 $             36,000.00 $   11,250.00
 10500 $                              58,500.00 $             47,250.00 $   11,250.00

 12000 $                              65,250.00 $             54,000.00 $   11,250.00
 10500 $                              58,500.00 $             47,250.00 $   11,250.00  EN 10000 HRS  $   56,250.00

                                          EN 11000 HRS        $   60,750.00
 MAXIMO  12000  $             65,250.00

 MINIMO  8000  $             47,250.00
 DIFERENCIA  4000  $             18,000.00



 TASA VARIABLE  $                                       4.50