GUARDERIA
METODO PUNTO ALTO Y BAJO
X Y EN 10000 HRS $ 56,250.00
HORAS DE MANO DE OBRA COSTOS DE PRODUCCION EN 11000 HRS $ 60,750.00
9000 $ 51,750.00
8000 $ 47,250.00
10500 $ 58,500.00
12000 $ 65,250.00
10500 $ 58,500.00
Fitted Line Plot
y = 11250 + 4.500 x
65000 S 0
R-Sq 100.0%
R-Sq(adj) 100.0%
60000
y 55000
50000
45000
8000 9000 10000 11000 12000
x