Page 75 - Angel Francisco Baca Escobedo
P. 75

GUARDERIA
                         METODO PUNTO ALTO Y BAJO
                         X                          Y                               EN 10000 HRS   $   56,250.00
            HORAS DE MANO DE OBRA        COSTOS DE PRODUCCION                       EN 11000 HRS   $   60,750.00
                                  9000 $                              51,750.00
                                  8000 $                              47,250.00
                                 10500 $                              58,500.00
                                 12000 $                              65,250.00
                                 10500 $                              58,500.00


                                                Fitted Line Plot
                                                y = 11250 + 4.500 x


                  65000                                                                S            0
                                                                                       R-Sq     100.0%
                                                                                       R-Sq(adj)  100.0%

                  60000




                y  55000



                  50000




                  45000
                         8000         9000          10000        11000         12000
                                                     x