2.4.2 Graphic Wall                                   wall graphics. Principal Contractor must ensure
                                                     that walls are in situ (but not necessarily finished)
In both new build and retro fit projects, the        prior to survey. Contractor must contact Printflow
graphic must cover one continuous wall in the        7 days prior to requiring installation, to arrange
customer area, over the drivers door (and any        the date. The graphic media is digitally printed
other doors), and terminate at the COLLECT           wall vinyl in ARTIST CANVAS – Class 0 fire rating.
end of the counter. The graphic wall must be
carefully prepared by the Principal Contractor       If a window is installed between the kitchen
before application of the vinyl by Printflow.        and customer area, then one-way Contravison
                                                     vinyl is to be applied to the glass to match with
A number of methods of preparation can be            the surrounding graphics. Supply and fitting by
used:                                                Printflow printed with the corresponding wall
                                                     graphic.
   1) Smooth plaster board wall with sanded
   taped and filled joints.                          Once the graphic wall has been fully installed,
   2) Smooth skim plaster finish. Wall to be sealed  Printflow must be requested to attend site and
   using PVA mix                                     survey the installation so that they can finalise and
   3) MDF lined wall where all joints and            print the graphic. This survey must be arranged
   countersunk screw heads, etc. have been           a minimum of 7 days prior to installation date. As
   filled using body filler and sanded flat          part of the graphic installation, Printflow will also
   4) Laminate lined wall using conte’ board or      install external corner protectors in brown.
   similar
                                                     Please note that there are a number of possible
Domino’s Design Team will no longer obtain           variations in the actual images used, so stores
a preliminary quote from Printflow during the        may not all contain the precise images shown in
project build up. The Franchisee or appointed        the examples. However installation procedures,
shopfitter MUST obtain quotes and place the          etc will be the same in all cases.
actual order with Printflow, no less than 3 weeks
prior to the required date of installation.
Printflow will then survey, design and install all