Page 183 - B6118-AEW-XX-XX-PP-A-0001_(P16)_Contractors Manual
P. 183

SUPPLY













         S1.2 IT Equipment, SOK’s and Tablet Tables

         The  IT installation  partner  will review site plans   3. At the completion of the project a final cost will
         and build the order on the Kelway ServiceTrack           be prepared by the IT Installer including any
         system following  the  completion  of  the  PSM          variations that occurred during the course of
         and site survey. Order completion is mandated            the Contract.  All variations to be agreed with
         minimum  seven  days  prior  to  the  first  fix  drop.   the Project PM through the Main Contractor.
         Further to a conference call with the IT Partners
         and Mark Currie/Ian Gibaud, we have prepared           4. If the programme for the Restaurant changes
         a pro-forma  and procedure for establishing              between Stage 2 programme and the actual
         costs for all Restaurants on the Programme.              site programme this shall be reported by the
                                                                  IT Partner  to  the  Main Contractor  with any
         Costs will be established as follows through the         variation in cost as a result of this revision and
         process using the standard pro-forma’s                   the Main Contractor shall then report this to
                                                                  the Project PM with a copy to the Project
         1. The Feasibility/Stage  One Cost will  be              QS for  a Contract  Variation, as and when
           established using the regularised costs agreed         appropriate.
           with the IT Partners,  which will relate  to  the
           type of Restaurant and the content of the IT
           Installation Works (as the attached Schedule).
           This cost will be circulated to the Project QS
           and the Project PM.

         2. Once the Restaurant  Programme  and
           content of the work has been established, at
           Stage  2,  a revised cost  will be  prepared  by
           the  IT  Partner  and this will include the  extra
           costs of any weekend working in accordance
           with the costs on the attached schedule.
           This will be the quotation for the IT installation
           Works and will be included in the Contracted
           Cost for the Restaurant.  Any variation to the
           standard Scenarios will be included in this cost
           for agreement by the Project PM.  This cost will
           be circulated to the Project Main Contractor,
           Project QS and Project PM.
















          S1.2           IT Equipment and SOK’s              4.0                        10 October 2017