Page 208 - B6118-AEW-XX-XX-PP-A-0001_(P19)_Contractors Manual
P. 208

SUPPLY













       S1.2 IT Equipment, SOK’s and Tablet Tables

       The  IT installation partner  will  review site plans   3. At the completion of the project a final cost
       and build the order on the Kelway ServiceTrack          will be prepared  by the IT Installer including
       system following the  completion of  the  PSM           any variations that  occurred  during  the
       and site survey. Order completion is mandated           course of the Contract.  All variations to be
       minimum  seven  days  prior to the first fix drop.      agreed with the Project PM through the Main
       Further to a conference call with the IT Partners       Contractor.
       and Mark Currie/Ian Gibaud, we have prepared
       a pro-forma and procedure  for  establishing          4. If the programme for the Restaurant changes
       costs for all Restaurants on the Programme.             between Stage 2 programme and the actual
                                                               site programme this shall be reported by the
       Costs will be established as follows through the        IT  Partner  to  the  Main  Contractor  with  any
       process using the standard pro-forma’s                  variation in cost as a result of this revision and
                                                               the Main Contractor shall then report this to
       1. The  Feasibility/Stage One Cost  will be             the  Project  PM with a copy to  the  Project
         established using the  regularised  costs             QS  for  a  Contract  Variation,  as and  when
         agreed with the IT Partners, which will relate        appropriate.
         to the type of Restaurant  and the content
         of the IT Installation Works (as the attached
         Schedule).  This cost will be circulated to the
         Project QS and the Project PM.

       2. Once the Restaurant Programme  and
         content of the work has been established, at
         Stage 2, a revised cost will be prepared by
         the  IT  Partner  and  this  will include  the  extra
         costs of any weekend working in accordance
         with the costs on the attached schedule.  This
         will be the  quotation  for  the  IT  installation
         Works and will be included in the Contracted
         Cost for the Restaurant.  Any variation to the
         standard Scenarios will  be included in this
         cost for agreement by the Project PM.  This
         cost will be circulated to  the  Project  Main
         Contractor, Project QS and Project PM.
















       S1.2            IT Equipment and SOK’s              4.0                        10 October 2017