Page 209 - B6118-AEW-XX-XX-PP-A-0001_(P19)_Contractors Manual
P. 209

SUPPLY





         S1 Free issue / direct suppliers






         S1.3 Contractor Order Website



         McDonald’s  have developed a bespoke                   The  system  will automatically direct  order
         ‘ordering’  system  for  their  nominated  supply      enquiries to the designated supplier appointed
         chain items. Principal Contactors  & Project           for  the  particular  product.    Where  multiple
         Managers will  be provided with system log in          suppliers  are used Contractors  will  need to
         details to enable them to:                             select the  correct  supplier for  the  project  as
         -  Browse  items and  place orders  per  project       notified  to  them  via  McDonald’s  Procurement
           (project information is  linked to the CotF          (as highlighted in the CotF programme) or via
           Programme)                                           liaison with their Project Manager.
         -  Browse  items and  place  orders  per  decor
           scheme or restaurant area (so free shopping          Bespoke  or  non-standard  parts  will still require
           in  any  concept  or  specific  area  such  as       offline  liaison  with  the  relevant  appointed
           externals, toilets or accessories)                   supplier for the particular concept.  Contractors
                                                                should liaise with their Project Managers or the
         It is envisaged that a project could be ordered        Procurement  Team if they are unsure  which
         in one session however the system allows for:          suppliers to send enquiries to.
         - Orders to be placed into a saved ‘draft basket’
           without having to be completed immediately           Nominated suppliers  will  politely refuse orders
           until all requirements are captured                  via any other  method  going  forward  as this
         -  Multiple orders  to  be  placed by project  as      resource  should  become  the  method  for
           required – so not holding up full orders if any      ordering products for McDonald’s projects.
           particular detail is subject to minor change
                                                                http://orders.mcdonaldsmandr.co.uk/login.
         The  system utilises the  CotF  programme  and         html
         will  issue  warning  notifications  to  Principal
         Contractors and McDonald’s Project Managers            Access information  to  the  website in terms  of
         where  late order  placement  could  jeopardise        usernames  & passwords should have already
         the critical  path. All enquiries made via  the        been supplied.  If you require access & have not
         ‘ordering’  system  will  be  confirmed  by  email     yet had these details please contact Paul May
         to  both  the  originator  of  the  enquiry  &  the    (paul.may@uk.mcd.com) for more details.
         respective suppliers.

         Goods are  invoiced either  to  McDonald’s in
         the traditional manner or where a contractor is
         due to pays for goods (such as floor or ceiling
         products) they must add invoice details to be
         able  to  complete  the  enquiry.    The  ‘ordering’
         system  will  not  deal  with  financial  transactions
         but will  highlight the possible  order  values for
         the project for both McDonald’s & Contractors
         alike.




          S1.3           Contractor Order Website             3.0                        14 December 2022
   204   205   206   207   208   209   210   211   212   213   214