CONSTRUCT
       CONSTRUCT




       C2 External Works






       C2.4 Installation of Tactile Paving

       400x400mm  Marshall’s blister (tactile) paving
       should be installed at designated pedestrian
       crossing  points,  identified  on  the  designer’s
       proposed site plan.

       Tactile paving must be set out in the direction
       of travel of the  crossing and not  necessarily
       perpendicular to  the  kerbline.  The  tactile
       paving must  provide a  colour  contrast  to  the
       surrounding  surface  finish  and  be  laid  in  two
       rows of three paviors with a central third line of
       two paviors as shown.






















































       C2.4            Installation of Tactile Paving      1.0                        08 October 2014