DPG Managed Build




        For  franchisees  who  may not  wish to  self-build, DPG  offer  an  enhanced  management  service,  providing
        additional support to the Franchisee throughout the project. For new store openings undertaken on a DPG
        managed basis, the DPG PM will provide the following services, over and above those listed in the ‘self-build’
        roles & responsibilities matrix:

                                        DPG PM
                                        Provide attendance at site visits by utilities companies and BT personnel as required.
                  Instructions          Appoint a Principal Designer in writing.
                                        Comply with all ‘Client’ duties which will fall to the franchisee under CDM Regulations 2015.
                                        Ensure that for all projects:
                                        - A Principal Designer is appointed
                                        - A Principal Contractor is appointed
                                        - Appropriate time and resources are allocated
                                        - Welfare facilities are provided
                                        Where not already in place, confirm appointment of Structural Engineer and any other
               Shop-fit Information     ‘specialist’ consultants as required.

                                        Notify relevant Building Control body of proposed start on site date and the construction
               Statutory Approvals      programme.
                                        Manage all Building Regulations Site Inspections & Site Certification Documentation.
                                        Tender the works - obtain quotations from approved contractors and suppliers using standard
                    Tender              template.
                                        Provide support to franchisee and contractor as required with regards to implementation of
                                        current brand standards and DPG shop fitting manual / design guides.
                                        Comply with all duties as ‘Client’ under the CDM Regulations 2015:
             Pre-start Anchor Meeting   Ensure that a PD is appointed
                                        Ensure that a PC is appointed
                                        Ensure that appropriate time and resources are allocated - any accidents or breaches of
                                        Health and Safety good practice due to lack of time or inadequate funding of appropriate
                                        safety measures may be deemed as the Clients fault by the HSE. Franchisees are advised to
                                        act responsibly regarding project programmes and budgets
                                        Ensure that welfare facilities are provided - franchisees may expect the Principal Contractor
                                        to provide welfare facilities during the site period. However, it is the franchisee’s responsibility
                                        as ‘Client’ to ensure that these facilities are provided
                                        Ensure that the Principal Contractor is sharing appropriate information with the design team
                                        and carrying out their coordination duties
                                        Take meter readings for all utilities supplies (gas, water and electricity) as applicable and log
                  Mobilisation          these at the time of Change of Tenancy (COT). This will help prevent the franchisee being
                                        incorrectly charged for usage prior to taking possession of the site.
                                        Provide attendance at site surveys / meter installations by utilities companies as required.
                                        Provide attendance at site surveys / installation dates by BT personnel as required.
                                        Place any direct orders with suppliers on behalf of the franchisee. Check all drawings and
                                        documents prior to placing orders for equipment.
                                        Provide information to the PC to allow adequate planning, management and co-ordination
                                        of the construction phase
                                        Ensure appropriate contents insurance cover is in place.
                                        Ensure plans for welfare facilities to be put in place prior to start on site.
                                        Notify Building Control
                  Start on Site         Manage all Building Regulations Site Inspections & Site Certification Documentation.

                                        Provide Principal Contractor with vacant possession of the site
                                        Ensure that welfare facilities are in place
                                        Follow agreed handover / inspection procedure with Principal Contractor on behalf of the
             Completion / Handover      franchisee.
                                        Receive O&M manual from Principal Contractor including as-fitted information. Collate all
                                        Health & Safety documentation and forward a copy to the DPG IT department for information
                                        and records.
                                        Oversee settlement of final account and confirm amount of any outstanding / final payments
            Post Completion Inspection  to be made by the franchisee, including release of retention.



                   Total fee payable by the Franchisee, for projects managed by DPG as described above is £3,250