Page 343 - B6118-AEW-XX-XX-PP-A-0001_(P15)_Contractors Manual_Neat
P. 343
CONSTRUCT
Ref Section Version Date
C3 Shopfitting 1.0 08 October 2014
C3.1 Stud Walls 2.0 09 February 2017
C3.2 Ceramic Tiling 2.0 09 February 2015
C3.3 Floor Movement Joints 1.0 08 October 2014
C3.4 Wall Tile Trims 1.0 09 February 2017
C3.5 Laminate Wall Panels 3.0 23 June 2016
C3.6 Wall Graphics 2.0 23 June 2016
C3.7 Low Modus Sealant 1.0 08 October 2014
C3.8 Ceilings 1.0 08 October 2014
C3.9 Furniture Fixing 3.0 25 July 2017
C3.10 Crew Lockers 2.0 15 January 2016
C3.11 Counter Gates 1.0 08 October 2014
C3.12 Internal Doors 1.0 08 October 2014
C3.13 Cubicles 1.0 08 October 2014
C3.14 IPS Panels 1.0 08 October 2014
C3.15 Vanity Pods 2.0 15 January 2016
C3.16 DT Welcome Zones 1.0 08 October 2014
C3.17 Digital Marketing Posters 2.0 25 July 2017
C3.18 McCafe Screens 3.0 25 July 2017
C3.19 Menu Boards 4.0 25 July 2017
C3.20 Counter Ceiling Raft; Adaptations 3.0 02 November 2016
C3.21 Counter Ceiling Raft; New 3.0 23 June 2016
C3.22 Dining Area Ceiling Raft 1.0 15 January 2016
C3.23 Digital Community Notice Boards 3.0 25 July 2017
C3.24 Public Awareness Monitors 2.0 25 July 2017
C3.25 Self Order Kiosks 3.0 25 July 2017
C3.26 Digi-play Projector Fixings 1.0 02 November 2016
C3.27 Isolated Floor Repairs (Modular Buildings) 2.0 15 January 2016
C3.28 Digital Screen Details 1.0 25 July 2017